Thursday, July 17, 2008

A Walk Around

Pastor Parrish writes...

The metal skeleton for the gym is just about finished and they will begin either the roof or insulating I imagine. The Construction company has about 5 men working this morning.

We dodged a bullet yesterday we trust. Duke power does not have 3 phase power available at our location. It is some distance to where they have it. The two 15 ton gas packs to run the gym will require 3 phase power. If we changed to Single phase they would have to split those into 4 units and spend additional funds for ducting and the additional units would be more expensive.

The Duke Engineer met with our electrician and us yesterday and has agreed to submit his request for Duke to build the lines for us to have the 3 phase power.

They will have to set additional poles near the line at the apartments next door and come up the back side of our property to leave our field area open for future building.

Ask The Lord to work on the Duke staff so the timing will work out on this project. If they can do this within a month we should be ready by then for the power. We will obtain temporary power prior to that for construction. Up to now they have used drop cords from our building and a generator and battery powered equipment.

Building Projects face many challenges.

God uses these to teach us many things.
Front View.
Side view near apartments.
Back view.

View from road behind the church showing rear entrance.