This was opening night at Master Club this past Wednesday. This room is where we have the opening and it seats over 30 kids.
Friday, December 19, 2008
Saturday, December 13, 2008
Monday, December 8, 2008
12-8-08 Monday Update
PRAISE THE LORD! We received our Final Occupancy Permit today from the City of Fort Mill! We are also thankful that the company doing our gym floor showed up early and are now currently finishing up the floor which should complete the building this week!
We are planning an open house very soon and will share the information when it is finalized.
Tuesday, December 2, 2008
Tuesday 12-2-08 Update
Its been quiet here the last week or so. We hit a snag with the gym floor. After the flooring crew were able to find a way for their floor to be installed they ran out of time and had to go do another job. They are expecting to be back and hopefully around December 15th we will be able to use it.
Most of the other issues have been resolved so we are almost ready to be able to use the gym.
Monday, November 17, 2008
Update Monday 11-17-08
We are getting closer to completion of the gym.
This is looking towards the entrance of the gym. Completed tile and finished paint.
The kitchen mostly finished.
Two classrooms with finished paint and carpet.
Looking from the entrance into the foyer.
Wide shot of the Foyer.
We had an inspection on Monday for our Certificate of Occupancy. It failed and there is a small list of things to fix and a few slight changes to make. We anticipate these being completed quickly and the Certificated given. Next week the gym floor will be completed and we anticipate the gym being completed by Thanksgiving!
Friday, October 31, 2008
Here are a couple of video updates. They show the foyer with freshly painted walls and doors hung. The kitchen with cabinets in place and gym bathroom with fixtures. Everything is progressing and we anticipate the first week of December the gym being complete.
Many thanks to Pastor Parrish and Pastor Jerry for their hard work in managing construction, meeting with contractors, electricians, plumbers, painters etc. Even unloading trucks and making runs to purchase and pick up appliances!
Monday, October 20, 2008
Update Monday 10-20-08
The gym with the lights on.
This is one of the bathrooms inside the gym.
The next few steps taking place will be tile in the kitchen, bathrooms and foyer. The cabinets will be hung in the kitchen. Painting will be finished up with carpet in the classrooms. The gym floor is last to be installed after everything else is finished.
This is one of the bathrooms inside the gym.
The next few steps taking place will be tile in the kitchen, bathrooms and foyer. The cabinets will be hung in the kitchen. Painting will be finished up with carpet in the classrooms. The gym floor is last to be installed after everything else is finished.
Thursday, October 9, 2008
Update Thursday 10-9-08

Its been a while since the last update, we have been waiting for Duke Power to finish up with the electricity. Yesterday they finished and the power is on at the gym.Since the lights are on the contractors have the green light to finish up on the inside of the gym. Our target date is Thanksgiving.
Note: Tours are available at 5:30pm on Sundays. See Pastor or Jerry.
Monday, September 29, 2008
Update Monday 9-29-08
Monday, September 22, 2008
Update Monday September 22, 2008
Here is the finished and striped parking lot on the right side of the gym.
As soon as the electrical lines are run painting can continue. With lights being accessible.
Sunday, September 14, 2008
Update Sunday 9-14-08
Here is the finished concrete around the front of the building. Paving should be completed on Monday.
The finishers are sanding the sheet rock and painters are to return this week and prime the gym.
Heat and air duct is going up in the gym and 3 of the 4 units have been set. The two 5 ton heat pumps that run the front rooms and restrooms etc. are being hooked up today they are 5 ton Trane heat pumps. The big rear units that run the gym will be 15 ton gas packs.
This is a close up to show the detail of the building. It is brick a quarter of the way up and Effice painted a tan color the rest of the way. Each window has a decorative feature above it.
Here is a video showing the inside. Some parts may be to dark. It was to dark to show the gym portion of the building that is straight back after going through the front door.
There is no sound.
As you walk through the front door there is a large foyer with four classrooms, two on each side. Then next is a storage room on one side and a kitchen on the other side. Inside the gym is access to the bathrooms (not pictured).
On Monday...
The paving crew is here and have begun paving. They cut 10 inches deep to get grade then put 8 inches of stone down and wet it and packed it until it was like concrete now they put 2 inches of pavement on top of that. We won't drive on it this week but by the next Sunday 28th we can begin to use it.
The finishers are sanding the sheet rock and painters are to return this week and prime the gym.
Heat and air duct is going up in the gym and 3 of the 4 units have been set. The two 5 ton heat pumps that run the front rooms and restrooms etc. are being hooked up today they are 5 ton Trane heat pumps. The big rear units that run the gym will be 15 ton gas packs.
Thursday, September 11, 2008
Update 9-11-08
This picture was taken Sunday Sept. 7th.
More pictures from the progress inside coming next week.
Monday, September 8, 2008
Update Monday 9-8-08
Click above to play.
With most of the exterior complete this shows the new sidewalk that was just poured. This week the grading should be completed.
Inside most of the sheet rock work has been completed and pictures will come soon showing that work.
Friday, September 5, 2008
Update Friday September 5, 2008
The scaffolding has been removed from the outside of the building. New pictures coming soon.
Pastor Parrish shares...
Thursday morning the construction company was pouring our 10 foot wide sidewalk along the 140 feet side of the building.
The Septic tank people did a good job and got the 240 feet of line in with just two lines 120 feet each which makes a better landscaping possible etc. and they just left finished today, Inspected and approved. I am sure glad that is over and done. State and county inspectors make me nervous.
The electricians mounted the wall box for Duke power to run their line to and they finished and cut the joints in the sidewalk. They framed up the pads for the 15 ton gas packs at the rear of the building and they will pour those and the floor around the Sprinkler riser inside the building and then frame up for the pad and side walk at the front of the building on Friday.
The gentleman doing the landscaping and grading and paving has been called and may begin the grading tomorrow.
Pastor Parrish shares...
Thursday morning the construction company was pouring our 10 foot wide sidewalk along the 140 feet side of the building.
The Septic tank people did a good job and got the 240 feet of line in with just two lines 120 feet each which makes a better landscaping possible etc. and they just left finished today, Inspected and approved. I am sure glad that is over and done. State and county inspectors make me nervous.
They still have a few sheets of sheet rock to hang in the gym and we added a small wall and door in the ladies restroom to cover up the Fire sprinkler riser that is a 6 inch pipe and gauges etc. That will cost an extra $1,000.
The electricians mounted the wall box for Duke power to run their line to and they finished and cut the joints in the sidewalk. They framed up the pads for the 15 ton gas packs at the rear of the building and they will pour those and the floor around the Sprinkler riser inside the building and then frame up for the pad and side walk at the front of the building on Friday.
The gentleman doing the landscaping and grading and paving has been called and may begin the grading tomorrow.
The sheet rock finishers are keeping up with the hangers pretty close so painting will not be to far behind.
Monday, August 25, 2008
Update Monday 8-25-08
This update shows the side of the gym being finished as they move to the top and front of the building.

Approximately 30 people toured the building Sunday evening before the service. Pastor Parrish shares this update...
"Insulation and the cement stucco was being worked on today at the gym. The lower half of the front was finished before the rain.
The inside insulation will be finished then an inspection must take place and then the rest of the sheet rock can be hung.
$2950 is the cost on the septic tank. Remember to pray for God's timing on it with the weather and 3 major underground lines that will be run: Natural Gas, Phone and Power.
The gym will have a monitored fire and burglar alarm system and a separate phone line with new number for the gym."
Monday, August 11, 2008
Tuesday 8-12-08 Update
Progress continues with the Gym. The projected date for it to be completed is November 1st. Remember though that is just the projected date and is subject to change. PTL for good weather as the outside of the building continues to show progress.
NOTE--To see a bigger picture of any that is posted just click on it. When finished select Back.
Below is the Effice Board being applied over the metal. It is installed then a concrete mix is added to it giving it a stucco look and then it will be painted the same as the trim of the Church.
This is the back of the building facing the apartments. The Effice board is installed and the concrete has been applied. Next is the painting.
Now for the inside.
The metal studs are in place and electrical boxes and lines are being run. This classroom is to the right as you walk in the front door.

This is the second class room to the right.
As you walk in and pass the class rooms on left this room will be the warming kitchen. As you look through the room behind it will be one of the bathrooms with shower.
Just past the class rooms on the right is this room which will be a storage closet with a bigger entrance. Again the room behind is part of the other bathroom that has a shower.
NOTE--To see a bigger picture of any that is posted just click on it. When finished select Back.
Below is the Effice Board being applied over the metal. It is installed then a concrete mix is added to it giving it a stucco look and then it will be painted the same as the trim of the Church.
The metal studs are in place and electrical boxes and lines are being run. This classroom is to the right as you walk in the front door.
This is the second class room to the right.