Friday, September 5, 2008

Update Friday September 5, 2008

The scaffolding has been removed from the outside of the building. New pictures coming soon.

Pastor Parrish shares...

Thursday morning the construction company was pouring our 10 foot wide sidewalk along the 140 feet side of the building.

The Septic tank people did a good job and got the 240 feet of line in with just two lines 120 feet each which makes a better landscaping possible etc. and they just left finished today, Inspected and approved. I am sure glad that is over and done. State and county inspectors make me nervous.

They still have a few sheets of sheet rock to hang in the gym and we added a small wall and door in the ladies restroom to cover up the Fire sprinkler riser that is a 6 inch pipe and gauges etc. That will cost an extra $1,000.

The electricians mounted the wall box for Duke power to run their line to and they finished and cut the joints in the sidewalk. They framed up the pads for the 15 ton gas packs at the rear of the building and they will pour those and the floor around the Sprinkler riser inside the building and then frame up for the pad and side walk at the front of the building on Friday.

The gentleman doing the landscaping and grading and paving has been called and may begin the grading tomorrow.

The sheet rock finishers are keeping up with the hangers pretty close so painting will not be to far behind.