The gym with the lights on.
This is one of the bathrooms inside the gym.
The next few steps taking place will be tile in the kitchen, bathrooms and foyer. The cabinets will be hung in the kitchen. Painting will be finished up with carpet in the classrooms. The gym floor is last to be installed after everything else is finished.
Monday, October 20, 2008
Thursday, October 9, 2008
Update Thursday 10-9-08

Its been a while since the last update, we have been waiting for Duke Power to finish up with the electricity. Yesterday they finished and the power is on at the gym.Since the lights are on the contractors have the green light to finish up on the inside of the gym. Our target date is Thanksgiving.
Note: Tours are available at 5:30pm on Sundays. See Pastor or Jerry.
Monday, September 29, 2008
Update Monday 9-29-08
Monday, September 22, 2008
Update Monday September 22, 2008
Here is the finished and striped parking lot on the right side of the gym.
As soon as the electrical lines are run painting can continue. With lights being accessible.
Sunday, September 14, 2008
Update Sunday 9-14-08
Here is the finished concrete around the front of the building. Paving should be completed on Monday.
The finishers are sanding the sheet rock and painters are to return this week and prime the gym.
Heat and air duct is going up in the gym and 3 of the 4 units have been set. The two 5 ton heat pumps that run the front rooms and restrooms etc. are being hooked up today they are 5 ton Trane heat pumps. The big rear units that run the gym will be 15 ton gas packs.
This is a close up to show the detail of the building. It is brick a quarter of the way up and Effice painted a tan color the rest of the way. Each window has a decorative feature above it.
Here is a video showing the inside. Some parts may be to dark. It was to dark to show the gym portion of the building that is straight back after going through the front door.
There is no sound.
As you walk through the front door there is a large foyer with four classrooms, two on each side. Then next is a storage room on one side and a kitchen on the other side. Inside the gym is access to the bathrooms (not pictured).
On Monday...
The paving crew is here and have begun paving. They cut 10 inches deep to get grade then put 8 inches of stone down and wet it and packed it until it was like concrete now they put 2 inches of pavement on top of that. We won't drive on it this week but by the next Sunday 28th we can begin to use it.
The finishers are sanding the sheet rock and painters are to return this week and prime the gym.
Heat and air duct is going up in the gym and 3 of the 4 units have been set. The two 5 ton heat pumps that run the front rooms and restrooms etc. are being hooked up today they are 5 ton Trane heat pumps. The big rear units that run the gym will be 15 ton gas packs.
Thursday, September 11, 2008
Update 9-11-08
This picture was taken Sunday Sept. 7th.
More pictures from the progress inside coming next week.
Monday, September 8, 2008
Update Monday 9-8-08
Click above to play.
With most of the exterior complete this shows the new sidewalk that was just poured. This week the grading should be completed.
Inside most of the sheet rock work has been completed and pictures will come soon showing that work.